Frequently Asked Questions

Question: Why is the construction of a new interchange at Highway 52/65th Street being proposed?
Answer: Without an interchange at Highway 52/65th Street, adjacent interchanges will not have enough capacity to accommodate future year 2035 traffic volumes. An interchange at this location, along with other local road improvements and auxiliary lanes, will help to balance the future traffic volumes between interchanges and avoid overloads at the Highway 52/55th Street interchange.

Engineering design and environmental documentation for the Highway 52/65th Street Interchange project are currently underway and the project is proposed for construction in 2012.

Question: Are there access spacing issues along Highway 52 if a new interchange is constructed at 65th Street?
Answer: The approximate distance between 55th Street and 65th Street is one mile and the approximate distance between 65th Street and 75th Street is one mile. Since this area of Rochester is considered a developing area in an urban setting, the proposed 65th Street interchange would meet Mn/DOT’s access spacing guidelines. However, a complete system of frontage roads and/or auxiliary lanes along Highway 52 becomes more important when interchanges are closely spaced, to minimize weaving and congestion on the mainline of the freeway.

Question: Why is the reconstruction of the Highway 52/55th Street interchange being proposed?
Answer: The current interchange configuration will not be able to accommodate the projected year 2035 traffic volumes on 55th Street. A new single-point interchange configuration, coupled with additional through-lanes and turn lanes in each direction on 55th Street will provide the needed capacity for the future traffic volumes.

Question: Why is the realignment of the East Frontage Road (Bandel Road) being proposed?
Answer: Realignment of the East Frontage Road (Bandel Road) is needed to provide more distance between the Highway 52/55th Street interchange and the intersection of 55th Street/East Frontage Road (Bandel Road). The increase in distance will allow additional turn lane storage and more efficient traffic flow on 55th Street.

Question: What is the status of the proposed West Frontage Road?
Answer: Currently, there are no plans for construction of a west frontage road along either the Clearwater Road or Chateau Road alignment within the NRTS 2035 timeframe. This decision was made based on public input, examination of social impacts of the west frontage road, and further evaluation of auxiliary lanes on Highway 52 between 55th and 65th Streets as a project alternative that provides acceptable traffic operations without construction of a west frontage road.

Question: Will there be auxiliary lanes constructed along Highway 52?
Answer: Auxiliary lanes along Highway 52 between 55th and 65th Street will be constructed as part of the Highway 52/65th Street Interchange project.

Question: Why is it important to keep local traffic off of Highway 52?
Answer: Highway 52 is considered a high priority regional corridor, with the main purpose of providing efficient connections between regional trade centers (i.e. Rochester to the Twin Cities). The safety, efficiency and capacity of this corridor are considered vital to the economic health of Minnesota. As this corridor becomes congested and less safe for travel, the cost of transporting goods and services between the trade centers increases. By introducing local trips, additional weaving on the freeway is created which decreases speed and safety along Highway 52.

Question: How many homes are proposed for acquisition and when will these homes be acquired?
Answer: A total of 9 properties will be affected by realignment of the East Frontage Road (3 of the 9 are residential properties that may need to be acquired). A total of 4 properties are affected by the 65th Street interchange (none of which are residential properties).

Property acquisitions can begin once the State of Minnesota and/or Federal Highway Administration (FHWA) approves the environmental documentation for individual projects and funding becomes available.

Question: What considerations are being made for bicyclists and pedestrians as part of the NRTS?
Answer: Trails are currently proposed along both sides of 55th Street and one side of 65th Street west of the proposed interchange.

Question: How will the proposed improvements affect air quality?
Answer: The construction of the recommended improvements is not anticipated to adversely affect air pollution in the area. Air pollution is typically at its worst when vehicles experience delays and are forced to idle. They NRTS shows that recommended improvements will actually reduce vehicle hours and vehicle miles traveled, thereby reducing delays and minimizing air pollution within the study area.

Question: How much will noise levels increase with the construction of the recommended improvements?
Answer: As part of the environmental documentation for each future project, a noise analysis will be conducted to determine noise levels and if there is a need for noise mitigation.

Question: What is the schedule for the NRTS project?
Answer: The NRTS has been completed and project phasing/staging was developed as part of the NRTS and will be documented in Technical Memorandum 6. Environmental document(s) will be prepared on a project by project basis.

Question: How will project staging/phasing be determined?
Answer: The project phasing/staging plan has been developed by the Project Management Team. Staging/phasing of the project was determined by analyzing which features of the project provide the most operational benefit, determining which features of the project are funded, and ensuring that the improvements fit into the long range plan for the area.

Question: How will these improvements be funded?
Answer: There is funding currently available for portions of the project. The City of Rochester has set aside funds for the construction of the ramps at the 65th Street interchange, for portions of 65th Street west of the proposed interchange and for 55th Street improvements in the proximity of Highway 52. However, funding for remaining improvements needs to be identified and secured.

Question: Who should I contact if I have further questions about the project?

Answer: Richard Freese
City of Rochester
201 4th Street SE
Rochester, MN 55904
rfreese@rochestermn.gov
(507) 328-2426
Jeffrey Bunch
Mn/DOT, District 6
2900 48th Street NW
Rochester, MN 55901
jeffrey.bunch@state.mn.us
(507) 286-7557